"Which one of the following best describes the critical path of a PERT/CPM network?
A. The sequence of activities between a project's start and finish that has the maximum amount of activity slack.
B. The set of activities that has no precedence relationships.
C. The sequence of activities that has the lowest normal activity cost.
D. The sequence of activities between a project's start and finish that takes the longest time to complete.
"
6 months agoReport content
Answer
Full Solution Locked
Sign in to view the complete step-by-step solution and unlock all study resources.
Step 1Let's solve this step by step:
Step 2: Understanding PERT/CPM Network Concepts
PERT (Program Evaluation and Review Technique) and CPM (Critical Path Method) are project management techniques used to analyze and schedule project activities.
Final Answer
The sequence of activities between a project's start and finish that takes the longest time to complete. Explanation: The critical path is the longest path through a project network, representing the minimum time needed to complete the entire project. Any delay in activities on this path will extend the total project duration.
Need Help with Homework?
Stuck on a difficult problem? We've got you covered:
- Post your question or upload an image
- Get instant step-by-step solutions
- Learn from our AI and community of students