Construction CDT Exam With Answers (175 Solved Questions)
- Civil Engineering
- 54 pages
- Shared May 2025
Get exam-ready with Construction CDT Exam With Answers, featuring authentic past exam papers with detailed solutions.
Preview 16 of 54 pages
See the first 16 pages exactly as they appear in the document.
Page 1 Read page 1 as text
CDT Exam questions Select the entity which is generally assigned the following duties and responsibilities by the Conditions of the Contract: Protection of job site workers and stored materials. A - Architect/Engineer B - Owner C - Contractor D - Varies, as stated in the Supplementary Conditions E - None of the above Reference: PDPG 5.4.1.7 and PDPG 15.12.11; EJCDC C - 700 Paras. 7.12 through 7.15; AIA A201 Sections 10.1, 10.2, and 10.4. Also see CCAPG 6.8; CCPG 9.14. Answer: C - Contractor. Safety provisions in both EJCDC and AIA documents clearly make safety and protection of persons and property at the construction Site the sole responsibility of the Contractor. Select the entity which is generally assigned the following duties and responsibilitie s by the Conditions of the Contract: Resolution of claims. A - Owner B - Contractor C - Varies, as stated in the Supplementary Conditions D - Initial Decision Maker Reference: PDPG 15.15.3; AIA A201 Sections 1.1.8 and 15.2. Also see CCAPG Chapter 10 (par ticularly CCAPG 10.3) Answer: D - Initial Decision Maker. The Initial Decision Maker is an entity that exists only in AIA documents and is not used in EJCDC documents. In AIA documents, when an entity other than the Architect is named as the Initial Decisi on Maker, said entity is identified in AIA A101 (Owner - Contractor Agreement) Section 6.1. In actual practice with AIA documents, the Initial Decision Maker is typically the Architect, but may be a third party considered to be neutral. select the entity whi ch is generally assigned the following duties and responsibilities by the Conditions of the Contract: Paying taxes for the Work. A - Architect/Engineer B - Owner C - Contractor D - Varies, as stated in the Supplementary Conditions E - None of the above R eference: EJCDC C - 700 Para. 7.09; AIA A201 Section 3.6; PDPG 13.6.4.4 among others. Also see CCAPG 3.1.4. Answer: C - Contractor. Taxes are part of the cost of construction for which the Contractor is responsible under the terms of the Contract Documents.
Page 2 Page 3 Read page 3 as text
For public work, where public owners are often exempt from certain sales and ues taxes on materials and equipment to be incorporated into the construction, typically an associated Supplementary Conditions provision is necessary to properly indicate the st atutory requirements for taxes, which can vary significantly from state to state. select the entity which is generally assigned the following duties and responsibilities by the Conditions of the Contract: Right to stop work, if non - conforming Work fails to be corrected. A - Architect/Engineer B - Owner C - Contractor D - Varies, as stated in the Supplementary Conditions E - None of the above Reference: PDPG 15.9.5.1; EJCDC C - 700 Para 14.06; AIA A201 Sections 2.4, 14.2 and 14.3. Also see CCAPG 2.1; CCAPG 6 .2.2; Answer: B - Owner. Standard contract documents such as EJCDC's and AIA's reserve to the Owner sole right to stop or suspend the Work if the Work does not comply with the Contract Documents. This right is solely the Owner's, and should never be assume d by or delegated to the A/E (or a construction manager), because stopping the Work is an extreme action that almost always results in a delay Claim from the Contractor for additional time and compensation. In EJCDC and AIA documents, the A/E does not have authority to stop or suspend the Work for non - conformance because issuing such an order is tantamount to opening the Owner's checkbook and handing out money. Which of the following is part of the construction documents but not part of the Contract Documen ts? A - Procurement Forms B - Agreement C - Performance Bond D - General Conditions E - Addenda F - Contract Modifications Reference: PDPG 12.1 and PDPG 12.2; EJCDC C - 700 Paras. 1.01.A.6 and 7; AIA A201 Section 1.1.1; and "The Diagram". Also see CCAPG 1. 3.1; CCAPG 8.2. Also see CSPG Chapter 9 Answer: A - Procurement Forms (also known as the Bid Form and its supplements). The Procurement (Bidding) Requirements, which include the advertisement or invitation to bid, instructions to bidders/proposers, bid for m, bid bond form (if any), qualifications statement (if any), and other bid form supplements (if any), are required only for the Project's procurement (bidding/pricing) stage and therefore are not typically considered to be "Contract Documents" (remember: "Contract Documents" exist only after the parties have both signed the Owner - Contractor Agreement).
Page 4 Read page 4 as text
If you are still having trouble wrapping your mind around this, consider that the Procurement (Bidding) requirements are necessary for, and apply only thro ugh, the procurement (bidding) stage — they address matters only until the Owner - Contractor Agreement is signed and the Contract becomes effective. Therefore, the Procurement (Bidding) Requirements are not necessary once the Contract is in effect. 46a: What is the "glue" that binds the Contract Documents together? Reference: PDPG 11.1.2; PDPG 11.1.5. Also see CSPG Chapter 5, "Agreements". Answer: If you answered "Agreement" you would not be entirely correct the correct answer is "signed Agreement" (see PDPG F igure 11.1) True or False: The Contracting Requirements include the performance bond. Reference: MasterFormat Division 00 (particularly 00 50 00 through 00 99 99); and "The Diagram". Answer: True. MasterFormat titles Division 00 as "Procurement and Contracting Requirements". Procurement (Bidding) Requirements are those documents that pertain only to the procurement (bidding) stage (e.g., advertisement or instructions to bidders, advertisement or invitation to bid, instructions to bidders/proposers, b id form, bid bond form (if any), bidder qualifications statement (if any), and other bid form supplements (if any). MasterFormat assigns these documents between 00 10 00 and 00 49 99. The "Contracting Requirements" are the balance of Division 00 (per Mast erFormat, documents between 00 50 00 and 00 99 99), including the Agreement form and its supplements (if any); project forms (including the performance bond and payment bond); "conditions of the contract"; and revisions/clarifications/modifications (includ ing Addenda). 46c: Project - specific insurance requirements would usually be included in the ____ (fill in the blank). Reference: PDPG 12.5. Also see CSPG Chapter 17 Answer: Supplementary Conditions. Project - specific insurance requirements, such as the spe cific types of insurance and minimum coverage limits required, are typically in the Supplementary Conditions. This is always the case with EJCDC documents, and was the case with AIA documents until the 2017 edition of AIA A201 and AIA A101. Both AIA A201 and EJCDC C - 700 (General Conditions) contain basic insurance provisions. But for the Owner to require that the Contractor furnish general liability insurance of not less than a certain coverage amount, or to require that the Contractor furnish a certain ty pe of railroad protective liability insurance, such requirements would be in the Supplementary Conditions (EJCDC C - 800, Supplementary Conditions, includes model language, as does AIA A503 — 2007). However, with its 2017 documents, the AIA extracted the speci fic requirements for certain types of insurance and created at new exhibit to AIA A101 (Owner - Contractor Agreement). Thus, as of 2017, AIA includes Project - specific insurance requirements in an exhibit to the Agreement. Also see EJCDC C - 700 Article 6 and EJCDC C - 800, Guide to the Preparation of
Page 5 Read page 5 as text
Supplementary Conditions, provisions numbered SC - 6.0x. Alternatively, see AIA A201 Section 11 and the insurance exhibit to AIA A101 — 2017. Note that EJCDC C - 800 and AIA A101 are not materials required for the CDT ex ams, but are extremely useful in the actual practice of preparing Supplementary Conditions. Arcadis US Water's Standard Supplementary Conditions ("Document 00 73 01") is developed closely from EJCDC C - 800. After evaluating a request for interpretation (RFI ), which of the following steps would not be applicable according to EJCDC: A - A/E responds directly on the RFI form B - A/E issues Supplemental Instructions C - A/E issues a Field Order D - A/E prepares a Proposal Request Reference: PDPG 15.11.1.2 and PDPG 15.11.2.1; EJCDC C - 700 Paras. 3.03 and 3.04; AIA A201 Section 1.1.1. Also see CCAPG 8.1.2 and CCAPG Chapter 9. Answer: B - Supplemental Instructions. The key to this question is understanding that EJCDC documents do not account for "Supplemental Instr uctions". Both EJCDC and AIA have a contractual mechanism for the A/E to order "minor changes" (changes that do not affect the Contract Price or Contract Times) in the Work; EJCDC calls it a Field Order (EJCDC C - 942) and the AIA calls the document "Archit ect's Supplemental Instructions" (AIA G710). When responding to a RFI, the A/E may provide a response directly on the RFI form (very common). Where the RFI response requires a minor change (no effect on price or time), a Field Order (EJCDC) or Architect's Supplemental Instructions (AIA) often accompanies the RFI response. Where the response to the RFI results in a potential change in price, time, or both, the RFI response should be accompanied by a Proposal Request. RFI responses, alone, should NEVER be u sed to attempt to modify the requirements of the Contract. RFI responses are not, themselves, Contract Documents. Which of the following is true regarding Conditions of the Contract: A - Are an inherent part of the Agreement B - Are an inherent part of th e specifications C - With the Agreement govern the content of the entire Contract D - Answers A and C E - None of the above Reference: PDPG 12.3.2, PDPG 12.3.3, and PDPG Figure 11.21; and "The Diagram". Also see CCAPG 1.3.1. Also see CSPG Chapter 6. Answe r: D - Answers A and C. "Conditions of the Contract" are, according to AIA and CSI (but not EJCDC) the General Conditions and the Supplementary Conditions. The
Page 6 Read page 6 as text
answer is not "B" because the General Requirements (not the Conditions of the Contract) administ ratively govern the Work indicated in the Specifications. Multiple - prime contracts are normally a part of: A - Turn - key construction B - Negotiated contracts C - Long duration construction projects D - Fast - track construction Reference: PDPG 5.8.4.2 and PDPG 11.4.1. Also see CCAPG 1.4.2. -------------------------------------- Answer: D - Fast - track construction. "Fast - track" does not mean only that the Contractor builds the project quickly, but rather is most - often used for describing projects where the c onstruction of "early - start" activities (such as site clearing, excavation, and foundation construction, for example) commence in the field while the A/E is still designing the rest of the project. Thus, the Contractor may be building the foundation and si te work (buried utilities, rough grading, etc.) while the A/E is still designing the facility's mechanical, plumbing, and electrical systems. In fast - track projects, the building may be divided among ten or more separate prime contractors. Coordinating mul tiple prime contracts is often very challenging and presents increased risk to both the Owner and A/E, particularly when design changes affect already - completed elements of the construction. In return, the Owner gets a project completed more - quickly, altho ugh likely for increased cost. In addition to using multiple - prime construction contracts for fast - tracking, multiple primes is required for most public works projects in certain jurisdictions, including New York State, Pennsylvania, and New Jersey. Prior to 2010, North Carolina essentially abandoned its multiple - prime public contracting requirement for public work and, in 2011, Ohio enacted legislation that significantly weakened Ohio's multiple - prime public contracting statutes. All other states in the U nited States allow public work to be constructed using a single prime construction contract. A submittal log should be maintained by: A - A/E B - Owner C - Contractor D - A and C E - All of the above Reference: PDPG 15.8.5 and PDPG 15.14. Also see CCAPG 5.8. Answer: D - A and C. Although all participants in the construction submittals process should track and log submittals for which they are responsible, the Contractor and A/E are responsible for, respectively, submitting and reviewing, all submittals re quired under the Contract Documents, and hence both have primary responsibility to track the status of submittals via a submittal log.
Page 7 Read page 7 as text
Both EJCDC and AIA documents require submittal logs, which are contractually the Contractor's responsibility. EJCDC C - 70 0 refers to this as a "Schedule of Submittals" and AIA A201 calls it a "Submittal Schedule". For additional information, refer to EJCDC C - 700's and AIA A201's provisions on the schedule of submittals. Neither, however, addresses the A/E's typical responsib ility to also track progress on the contractually - required submittals. The Procurement Documents include all of the following EXCEPT: A - Procurement Requirements B - Contract Modifications C - Project Manual D - Drawings Reference: PDPG 11.1 and PDPG Chapter 12; EJCDC C - 700 Para. 1.01.A.6 and 1.01.A.7; AIA A201 Section 1.1.1; and "The Diagram". Also see CCAPG 1.3.1; CCAPG 8.2. Also see CSPG Chapter 9. -------------------------------------- Answer: B - Contract Modifications. Procurement (Bidding) Docum ents are issued for the procurement (bidding/pricing) stage, before there are any "Contract Documents" (e.g., before the Owner - Contractor Agreement is signed); thus, there is no "contract" to modify until the Agreement is signed by both parties. The way th at the Procurement (Bidding) Documents are modified prior to the opening of Bids is via Addenda. A Construction manager is hired by the Owner to do all of the following except: A - Assist in procuring the contractor B - Administer the project C - Provide observation services at the construction site D - Supervise the A/E Reference: PDPG 7.4. Also see CCAPG 1.4.2. Also see CSPG 1.14.2. Answer: D - Supervise the A/E. However, this question is difficult because the extent to which Answers "A", "B" and "C" ar e true or false depends on the form of construction manager project delivery. Answer "A" is true for CMa - construction manager as an advisor. Answer "A" is false for CMAR - construction manager at risk (where the construction manager becomes the general contractor upon the start of construction), because the CMAR is the Contractor and would monitor Subcontractors (e.g., instead of the CM monitoring the Contractor). Answer "B" is sometimes true — for example, in standard documents from the Construction Mana gement Association of America (CMAA) and AGC's ConsensusDocs the CM is given authority to act on the Owner's behalf. However, in standard documents by the AIA and in EJCDC's forthcoming CMa - Series documents, the CM does not have authority to act on the Own er's behalf. Answer "C" is typically true for CMa project delivery. In CMAR delivery, the CMAR is the
Page 8 Read page 8 as text
contractor and therefore supervises the construction instead of merely observing the Work. Answer "D" is always false because the CM never supervises th e Architect or the Engineer. Because they are required to have a professional license and registration in the state(s) where they practice, A/Es cannot, by definition, be "supervised" by anyone who does not want to assume the A/E's professional liability. Thus, Answer "D" is the correct choice for this question. A facility's "life cycle" includes all of the following EXCEPT: A - Project Conception B - Financing C - Construction D - Facility Management Reference: PDPG Chapter 2 (especially PDPG 2.2). ----- --------------------------------- Answer: B - Financing. Answer choices "A", "C", and "D" are all part of the facility's life cycle as defined by CSI in PDPG 2.2; being familiar with CSI's "facility life cycle" concept will likely be worth a few points on the CDT exam. While "financing" is a stage of the facility life cycle as defined by the Associated General Contractors of America (AGC); however, AGC's ConsensusDocs documents are not the basis for any of CSI's exams. "Resource drawings" serve which purpo se? A - Show existing work that is to be modified B - Show construction related to the work, but which is not included in the contract C - Provide the owner with a set of documents that will facilitate operation D - Drawings prepared by manufacturers, sup pliers, and the contractor to illustrate portions of the work Reference: PDPG 11.2.4. Also see CCAPG 1.3.2.1. Answer: B - Show construction related to the work, but which is not included in the contract. Although resource drawings are included by some A/E 's in the "information available to Bidders" in the Procurement (Bidding) Requirements (MasterFormat assigns "00 31 16, Measured Drawing Information", among others), Arcadis US Water discourages issuing resource drawings, measured drawings, or existing rec ord drawings as part of the Bidding Documents, or binding them into the Project Manual. EJCDC C - 700 Paras. 5.03.B and 5.06.B expressly state that reports and drawings of existing subsurface and physical conditions, and reports and drawings of a Hazardous Environmental Condition at the Site are not Contract Documents. Answer "A" is nebulous; existing facilities to be modified will typically be shown on the
Page 9 Read page 9 as text
Drawings that are part of the Contract Documents. Answer "C" is describing record documents. Answer " D" is describing Shop Drawings. 25. For this question, select the entity which is generally assigned the following duties and responsibilities by the Conditions of the Contract: Paying taxes for the Work. A - Architect/Engineer B - Owner C - Contractor D - Varies, as stated in the Supplementary Conditions E - None of the above Reference: EJCDC C - 700 Para. 7.09; AIA A201 Section 3.6; PDPG 13.6.4.4 among others. Also see CCAPG 3.1.4. Answer: C - Contractor. Taxes are part of the cost of construction for whi ch the Contractor is responsible under the terms of the Contract Documents. For public work, where public owners are often exempt from certain sales and ues taxes on materials and equipment to be incorporated into the construction, typically an associated Supplementary Conditions provision is necessary to properly indicate the statutory requirements for taxes, which can vary significantly from state to state. For this question, select the entity which is generally assigned the following duties and responsi bilities by the Conditions of the Contract: Right to stop work, if non - conforming Work fails to be corrected. A - Architect/Engineer B - Owner C - Contractor D - Varies, as stated in the Supplementary Conditions E - None of the above Reference: PDPG 15.9 .5.1; EJCDC C - 700 Para 14.06; AIA A201 Sections 2.4, 14.2 and 14.3. Also see CCAPG 2.1; CCAPG 6.2.2; Answer: B - Owner. Standard contract documents such as EJCDC's and AIA's reserve to the Owner sole right to stop or suspend the Work if the Work does not c omply with the Contract Documents. This right is solely the Owner's, and should never be assumed by or delegated to the A/E (or a construction manager), because stopping the Work is an extreme action that almost always results in a delay Claim from the Con tractor for additional time and compensation. In EJCDC and AIA documents, the A/E does not have authority to stop or suspend the Work for non - conformance because issuing such an order is tantamount to opening the Owner's checkbook and handing out money. W hile EJCDC's and AIA's standard documents empower the A/E to "reject defective Work" (i.e., refuse to recommend payment for such Work and refuse to accept defective Work, thus keeping the Contract open, but the A/E does not have the authority to stop or su spend the Work. Only the Owner has the authority to order the Contractor to stop or suspend the Work.
Page 10 Read page 10 as text
EJCDC C - 700 Para. 1.02.D defines "defective Work" as follows: "The word "defective," when modifying the word "Work," refers to Work that is unsatisfactor y, faulty, or deficient in that it: (a) does not conform to the Contract Documents; or (b) does not meet the requirements of any applicable inspection, reference standard, test, or approval referred to in the Contract Documents; or (c) has been damaged pri or to Engineer's recommendation of final payment (unless responsibility for the protection thereof has been assumed by Owner at Substantial Completion in accordance with Paragraph 15.03 or 15.04)." 21. All of the following are AIA construction contract mod ifications EXCEPT: A - Change Order B - Architect's Supplemental Instructions C - Field Order D - Construction Change Directive Reference: PDPG 15.11.2.1; EJCDC C - 700 Paras. 1.01.A.21 and 11.01; AIA A201 Section 1.1.1. Also see CCAPG 8.2. Also see CSPG C hapter 9 — particularly CSPG 9.6. -------------------------------------- Answer: C - Field Order. While a Field Order is not a document used or recognized by the AIA, it is defined at EJCDC C - 700 Para. 1.01.A.21. EJCDC publishes a standard field order form, EJCDC C - 941 ("Field Order"); CSI also publishes a field order form. Both a Field Order (EJCDC, DBIA, CSI) and "Architect's Supplemental Instructions" form (AIA G710) are used by the A/E to order minor changes in the Work that do not result in changes in th e Contract Price or the Contract Times; although there are some minor differences between them, the use of both a Field Order and AIA's "Architect's Supplemental Instructions" form are similar. . For this question, select the entity which is generally assi gned the following duties and responsibilities by the Conditions of the Contract: Furnishing property insurance for the work under construction: A - Architect/Engineer B - Owner C - Contractor D - Varies, as stated in the Supplementary Conditions E - None of the above Reference: PDPG 12.5.2; AIA A201 Section 11.2.2; AIA A101 Insurance Exhibit Section A.2.3 (AIA A101 and its related insurance exhibit document are not source materials for the CDT exam). Also see CSPG 17.4, which is a comprehensive introduct ion to property insurance. -------------------------------------- Answer: B - Owner. Construction property insurance is a separate policy from the Contractor's and Owner's own general liability policies; property insurance covers losses to the Work and oth er property at the Site. There are two broad types of property insurance: (1) "normal" property insurance, maintain by the property's owner, and (2)
Page 11 Read page 11 as text
construction stage property insurance covering the materials and equipment to be incorporated into the cons truction, typically called, "builder's risk" insurance. Builder's risk insurance is typically in effect only through Substantial Completion of the construction, after which property insurance coverage should be transitioned to the Owner's regular property insurance policy. Builder's risk insurance is typically desirable when the Project includes construction of or modifications to some type of structure or building. A special form of builder's risk insurance — called an "installation floater" — can be obtained to cover materials to be installed into construction that is not in a building or structure; for example, for protection against loss to waterline pipe stored trench - side. PDPG 12.5.2 presents a basic overview of property insurance, and indicates that th e Owner "typically" obtains the builder's risk insurance. AIA A201 implies, and AIA A101 - Insurance Exhibit states that the Owner furnishes the builder's risk insurance unless expressly indicated otherwise in the Contract. In private work, it is perhaps mos t - common for the Owner to furnish the builder's risk insurance, and thus the best answer choice is "B - Owner". That said, many projects, including most public works projects, require that the Contractor furnish the builder's risk insurance. In fact, this is the default requirement of EJCDC C - 700 Para. 6.05. The reality is that public owners typically desire to not procure builder's risk insurance. But in certain circumstances — such as work to modify or rehabilitate an existing facility that remains in ope ration during construction — it may be advantageous to the Owner to furnish the builder's risk insurance. In the event of a loss under the builder's risk policy, the Owner can coordinate with its own property insurance to proceed swiftly toward having the lo ss remedied and to get the facility back into service, as opposed to having to work with both the Owner's normal property insurance carrier and the Contractor's builder's risk insurance carrier. However, each project is different and Owner's preferences an d direction relative to the procurement of builder's risk insurance are to be respected by the A/E or other entity drafting the construction documents' Division 00 requirements (where provisions on insurance are located). Insurance is a very complex topic and most A/Es and owners' project personnel are typically unfamiliar and perhaps uncomfortable with the topic. However, it is important for A/Es and owners to understand the basics of construction insurance. CSI's PDPG and CSPG present very good, basic ov erviews of the topic. In the coming weeks we will also share with our CSI Program participants some supplemental information on the "arcane" but vital topic of construction insurance. The Owner should always direct the A/E in the types of insurance and co verage amounts required. EJCDC C - 051 and EJCDC C - 052, or AIA G612 are useful documents for documenting the Owner's instructions relative to insurance requirements.
Page 12 Read page 12 as text
A/Es are design professionals — not risk advisors or insurance counselors — and should avoid giv ing, and appearing to give, insurance advice. 1. What establishes the relationship between the Contractor and the Architect/Engineer (A/E)? A - National laws B - Signed agreements C - Third - party obligations D - Special conditions Reference: See PDPG Sec tion 5.2 ("PDPG 5.2") and PDPG Figure 5.1. -------------------------------------- Answer: C - Third - party obligations. The Contractor and the A/E do not have any signed agreements, the general terms and conditions of their respective contracts with the Own er provide them with third party obligations to each other. 5. Which of the following would be included in the Information Available to Bidders? A - Bid Security information B - Environmental Impact Statement C - Time of completion to construct the Projec t D - Description of the Work Reference: PDPG 12.2.3, and CSI MasterFormat 00 03 00. -------------------------------------- Answer: B - Environmental Impact Statement. The information available to Bidders is the place to provide reference information that does not belong in the "Contract Documents". Bid security information is included in the Instructions to Bidders. Time of completion ("Contract Times" in EJCDC, "Contract Time" in AIA documents) is an important contractual obligation — where would you thi nk it should go? (Hint: in neither the Instructions to Bidders nor the information available to Bidders). Okay...we'll tell you. It's in the Owner - Contractor Agreement. Description of the Work is included throughout the construction Contract Documents, an d is summarized in a Division 01 Specifications can you name the Division 01 Section? (Hint: It's in a section called, "Summary of Work"). What constitutes the "Contract Documents" is a very important concept, and we'll share some supplemental information on that very soon. Also important is the concept of "information available to bidders" — such as information on subsurface conditions (like soil borings), information on the presence of hazardous substances at the Site, and use of existing record documents. We will also distribute some supplemental information on this important topic as well.
Page 13 Read page 13 as text
6. The contractual relationship governed by the Conditions of the Contract is between: A - Owner and Contractor B - Architect/Engineer and Contractor C - Owner and Sub contractors D - Architect/Engineer and Subcontractors Reference: PDPG 12.3.3. Also see CSPG Chapter 6 and CCAPG 1.3. Answer: A - The Owner and the Contractor. The Owner and the Contractor are the parties to the construction Contract, and hence are the pri ncipal subjects of the "Conditions of the Contract". "Conditions of the Contract" is AIA's and CSI's term for the "General Conditions and Supplementary Conditions". Yes, the duties of the A/E are described to a large (but not necessarily full) extent in th e "Conditions of the Contract", but the A/E's responsibilities are fully and properly set forth in the Owner - A/E Agreement. The Owner - A/E Agreement does not have General Conditions or Supplementary Conditions. EJCDC's standard "Conditions of the Contract" (note: the term "Conditions of the Contract" is not used in EJCDC standard contract documents and, hence, should not be used in association with Arcadis U.S. Water's Standard Construction Documents; but you will see the term on CSI's exams; "Conditions of the Contract" is an AIA term) are EJCDC C - 700, Standard General Conditions of the Construction Contract, and EJCDC C - 800, Guide to the Preparation of Supplementary Conditions. AIA's corresponding standard Conditions of the Contract are AIA A201, Standard General Conditions of the Contract for Construction, and AIA A503, Guide for Supplementary Conditions. EJCDC C - 700 is the standard general conditions used by Arcadis U.S. Water for construction contracts. Arcadis U.S. Water's Standard Supplementary Condit ions are very - closely based on EJCDC C - 800. EJCDC C - 700 and EJCDC C - 800 are the most widely - used "Conditions of the Contract" for engineer - led projects (especially for public work) in the United States for design - bid - build delivery. AIA A201 and AIA A503 a re the most - widely used "Conditions of the Contract" for vertical (architect - led) construction (design - bid - build) in the United States. Other nations have their own, popular standard construction contracts. In Canada, the documents of the Canadian Constru ction Documents Committee (CCDC) are widely used by both architects and engineers. Still others are used in the UK and Europe, and elsewhere. Takeaways: (1) there are many types of standard construction documents such as AIA and EJCDC, and (2) for design - bid - build delivery, as well as construction manager as advisor (CMa) and construction manager as contractor (CMc), the "Conditions of the Contract" are part of the Owner - Contractor Contract. 7. A unit price contract is used when: A - Extent of the Work ca nnot be fully determined or where actual quantities cannot be
Page 14 Read page 14 as text
accurately calculated prior to construction B - Extent of the Work is known, but the Owner desires a unit cost for portions of the Work C - It is anticipated that Bidders will not examine soil b earing reports prior to submitting their Bid D - Bidding quantities of equipment Reference: PDPG 13.10.5; PDPG 13.8.3; also PDPG 12.2.4 (procurement forms). Also see CCAPG 11.3 and 11.5. Also see CSPG 7.8; and CSPG 7.5.2. --------------------------------- ----- Answer: A - Extent of the Work cannot be fully determined or where actual quantities cannot be accurately calculated prior to construction. Use of unit prices, allowances, or alternates should always be limited to those items required for accurate bi dding/pricing, to keep the Bidding Documents and processes as simple as possible. . An addendum cannot be used to change the: A - Contract Sum B - Date and time for receipt of Bids C - Quality of the Work D - Quantity of the Work Reference: and PDPG 13.4 .2.8 and 15.11.2.3, and EJCDC C - 700 Paragraph 1.01.A.1; AIA A201 Section 1.1.1. Also see CCAPG 8.3. Also see CSPG 9.4. -------------------------------------- Answer: A - Contract Sum. Why, you ask? Because Addenda are issued during the bidding (procurement ) stage (see Question No. 8), before there is a signed Contract between the Owner and Contractor, and therefore, are issued before there is a Contract Sum. When issued prior to the receipt of Bids (or, with AIA documents, prior to the signature of the Owne r - Contractor Agreement), an Addendum can be used to change the date for receipt of Bids, the required quality of the Work, and the scope or extent of the Work. . What would one use to change the Contract Price (Contract Sum in AIA documents)? Hint: It's no t an Addendum. For more on how the Contract Price/Contract Sum is modified, see PDPG 15.11.2.3, CCAPG 8.3, CSPG 9.4; EJCDC C - 700 Paras. 11.02, 11.04, and 11.05; and AIA A201 Sections 7.1 and 7.2. 10. Which of the following is a true statement about addenda ? A - They typically arise from a change order B - They are part of the contract documents C - They are listed in Division 01 - General Requirements D - They can be issued at any time during the contract period Reference: PDPG 13.4.2.8; EJCDC C - 700 Para 1.01.A.13 and EJCDC C - 520 Para. 9.01; AIA A201 Section 1.1.1 and AIA A101 Section 9.1; and "The Diagram". Also see
Page 15 Read page 15 as text
CCAPG 1.3.1. -------------------------------------- Answer: B - They are part of the contract documents. This one is a little tricky. During the procurement (bidding) stage, there is no Contract, and because Addenda are issued during the procurement (bidding) stage, how can they be part of the Contract Docu ments? Well, they BECOME part of the Contract Documents when the Owner - Contractor Agreement is signed. While the answer says they "ARE" part of the Contract Documents, they are at a point in time after signing the Owner - Contractor Agreement. All of the oth er choices to this question are COMPLETELY wrong, so Answer "B" is the best answer out of the choices available. For a list of what constitutes the "Contract Documents", see EJCDC C - 520 (Owner - Contractor Agreement), Paragraph 9.01, and AIA A101 (Owner - Con tractor Agreement), Articles 1 and 9, and AIA A201 Paragraph 1.1.1. 11. Select the entity which is essentially assigned the following duties and responsibilities by the Conditions of the Contract - Furnishing surveys and utility locations: A - Architect/E ngineer B - Owner C - Contractor D - Varies, as stated in the Supplementary Conditions E - None of the above Reference: PDPG 12.2.3.1; EJCDC C - 700 Paras. 4.03 and 5.05, and AIA A201 Sections 2.3.4 and 2.3.5. Also see especially CCAPG 3.8.9 and 3.8.10. Als o see EJCDC E - 500 (Owner - Engineer Agreement) Para. B2.01.D (in Exhibit B), and AIA B101 (Owner - Architect Agreement) Section 5.4 Answer: B - Owner. Because the Owner furnishes the Site for the Contractor to construct the Work, the Owner is in the best posit ion to have available and furnish surveys and utility locations. It is common, however, for the Owner to make obtaining and furnishing to the Contractor such information part of the A/E's scope of professional services. However, as the entity in control o f the Site — particularly for remodeling or rehabilitation of an existing facility — the Owner should maintain a complete file of information about its own property, including surveys, utility information, reports of previous investigations of subsurface condi tions and the presence at the Site of a Hazardous Environmental Condition (including the presence of common substances such as asbestos, lead - based paint, and PCBs), and record drawings of existing conditions. 12. Which of the following documents would typ ically not be produced during the schematic design phase of the Project's Design Stage? A - Sketches B - Outline specifications C - Models
Page 16 Read page 16 as text
D - Preliminary project descriptions Reference: PDPG 2.2 and 2.3; and PDPG 9.4, 9.12, 9.13. 9.14, and PDPG 11.1 and 11.3.11. -------------------------------------- Answer: B - Outline specifications. PDPG 9.14.2 expressly states that outline specifications are developed during the design development phase. Especially refer to PDPG 9.12 through 9.14 and PDPG 11.1 and P DPG 11.3.11 (knowledge of these sections could be worth several points on the CDT exam). It is very important understand that different entities (such as CSI, EJCDC, and AIA, among others) have different terms for parts of the Project's design stage, as s et forth in PDPG 2.3. Answer choices "sketches" and "preliminary project descriptions" are clearly prepared during the schematic design phase, as indicated in PDPG 9.13 and PDPG 11.3.11. "Scaled models" are also prepared during the schematic design phase per PDPG 9.13.1. (In 2010, CSI published an entire book with suggested formats for preliminary project descriptions, titled PPDFormat, which is not a required study item for the exams.) AIA B101 defines "schematic design phase", "design development phase" , and "construction documents phase". EJCDC E - 500 defines the following phases: "study and report phase" (not part of "design"), "preliminary design phase", and "final design phase". As noted in PDPG 2.3, other industry - standard documents (not covered on t he CDT exam) contain yet other variations on these terms! In 2011 CSI standardized (more - or - less) on AIA's terms (schematic design, design development, and contract documents phase); EJCDC divides the design stage into two parts: "preliminary design" and "final design". For the exam, be familiar with CSI's terms in PDPG; for actual practice within the Arcadis U.S. Water Business Line, be familiar with (and use) the terminology in EJCDC documents. 13. Allowances, alternates, and unit prices are used to con trol all of the following EXCEPT: A - Indeterminate items B - Postponement of decisions C - Contractor selection D - Construction costs Reference: PDPG 13.8 and PDPG 13.4.2.13. Also see CSPG 7.6, 7.7, and 7.8. Answer: C - Contractor selection. Under the design - bid - build project delivery method, Contractor selection is determined during the procurement (bidding) stage, whether by
38 more pages in the full document
Unlock it once and it stays in your library, ready to chat with or turn into flashcards.
Unlock the full documentMore Civil Engineering study materials
See all
Textbook GuidesSolution Manual for Transportation Engineering and Planning, 3rd Edition
Civil Engineering
78 pages92downloadsFeb 2025
Textbook GuidesReinforced Concrete Design, 9th Edition Solution Manual
Civil Engineering
198 pages65downloadsFeb 2025
Exam GuidesPrinciples Of Foundation Engineering, 8th Edition Test Bank
Civil Engineering
166 pages49downloadsFeb 2025
Textbook GuidesSolution Manual for A First Course in the Finite Element Method, 6th Edition
Civil Engineering
644 pagesMay 2025
Past ExamsThe CE Shop Construction Final Exam With Answers (100 Solved Questions)
Civil Engineering
55 pagesMay 2025
Textbook GuidesSolution Manual for Structural Steel Design, 6th Edition
Civil Engineering
511 pagesMay 2025
Textbook GuidesSolution Manual For Structural Wood Design: ASD/LRFD, 2nd Edition
Civil Engineering
268 pagesMay 2025
Past Exams2023 CLC059 Construction Practice Exam With Answers (39 Solved Questions)
Civil Engineering
12 pagesMay 2025
Study this document with CramX
Once it is in your library, every tool can work from it.